1、一份船舶建造合同YACHT BUILD AGREEMENTDATED: 22nd December 2002betweenAAAs Yacht Company Limited, Hong Kong. Hereinafter referred to as “the BuilderandBBB CC, Vietnam, Hereinafter referred to as “the BuyerWHEREAS:1 The Buyer wishes to acquire a AAAs Cape 65 Trawler Yacht the yacht designed by Thanos Condylis

2、, and built to the Buyers stated requirements and specification, and the Builder has the capability, knowledge and skills to build and supply the same.2 The Builder has agreed to construct, equip, fit-out, test and deliver the Yacht to the Buyers stated requirements and specification, which the Buye

3、r has agreed to accept upon the terms and conditions here in after specified:Now therefore the Parties hereto have agreed and do hereby agree as follows:ARTICLE I - INTERPRETATION1 In this Contract the following words and expressions shall have the meaning hereby ascribed to them, except where the c

4、ontext otherwise admits or requires:“Banking Days Shall mean days upon which Hong Kong clearing banks are customarily open for business.“the Builders Clarifications Shall mean the documents so entitled forming part of this Contract and set out as Annexes hereto; See also Item 2 of this Article.“Buye

5、rs Representatives Shall mean such persons notified from time to time by the Buyer as having authority to act for the Buyer, the extent of such authority being set out in the notice;“Items of Buyers supply Shall mean any item of equipment and stores for the Yacht ordered by the Buyer direct from the

6、 manufacturer or the supplier, for incorporation in the Yacht by the Builder;“Items of Builders supply Shall mean any item of equipment and stores for the Yacht ordered by the Builder direct from the manufacturer or the supplier, for incorporation in the Yacht;“the Certifying / Survey Body Shall mea

7、n the body responsible for the survey and certification of the yacht to the requirements of the buyer.“the Contract Shall mean a this Contract, and b the attached Annexes and schedule more particularly described below.“the Contract Delivery Date Shall mean no later than 30 June 2002;“the Contract Ma

8、ster Programme Shall mean the programme for construction of the Yacht, set out in Annex D;“the Contract Price Shall mean the price stipulated in Article V for the Yacht, Yard Number 005;“the Yacht Shall mean the yacht the subject of this Contract and generally as described in Article II, with all th

9、e machinery, apparatus, outfit, materials, and equipment appurtenant thereto, but excluding the items of Buyers supply.“the Boatyard Shall mean AAAs Yacht Company, Xinhui, China.“the Design Specifications Shall mean the specifications, designs, plans and drawings, set out in Schedule A, prepared and

10、 signed by the Buyer, identified as forming part of this Contract, and including such revised or supplemental specifications, plans and drawings as may subsequently be agreed between the Buyer and the Builder PROVIDED that i in the case of any inconsistency between any Article or paragraph of this C

11、ontract and the Design Specifications, this Contract shall prevail, ii in the case of any inconsistency between the Design Specifications and a plan or drawing, the Design Specification shall prevail, and iii in the case of any inconsistency between one plan or drawing and another plan or drawing, t

12、he later in date shall prevail;"Schedule A" Shall mean the agreed schedule of drawings“Annex A Shall mean the list of materials, components and equipment defining a completed yacht;"Annex B" Shall mean the agreed weld quality procedures“Annex C Shall mean the agreed Shot Blasting

13、, Fairing, Painting and foaming Specifications"Annex D“ Shall mean the agreed production schedule master program.“Specified Shall mean stipulated in the specifications and Annex A;“Supplier Shall mean any person, firm or company, which has entered into a contract with the Builder for the supply

14、 of materials, machinery, services or equipment other than items of Buyers supply for the yacht;The Index, Article and paragraph headings, are inserted for convenience only and shall not affect the construction of this Contract.Words importing the singular shall include the plural and vice versa.2 L

15、ist of Builders clarifications, not covered in Annex A document:“Cradles for Transport The supply of a Cradle for shipment is excluded from this Contract.“Dressing/Stepping the Mast The dressing and stepping of mast for the Yacht is included in the Builders supply.“Storage The Builder will arrange secure storage ashore for the Yacht at the Boatyard between completion of build and handover at delivery.